STS-99
|
Shuttle to the Launch Pad |
'99/12/13 |
|
|
|
Helium signature leak test |
'00/1/7 |
|
|
|
Prelaunch propellant loading |
'00/1/10-12 |
|
|
|
Aft compartment close-outs |
|
'00/1/13 |
|
|
Terminal Countdown Demonstration
Test (TCDT) |
'00/1/13-14 |
'00/1/14 |
|
|
Prelaunch propellant loading concludes |
|
'00/1/15 |
|
|
Flight
Readiness Review |
|
'00/1/18 |
|
|
Ordnance
installation begins |
|
'00/1/24 |
|
|
Flight
crew equipment stowage begins |
|
'00/1/25 |
'00/1/26 |
|
Orbiter
aft comparment close-outs |
|
|
'00/1/26 |
| @ |
Flight
crew arrives at KSC |
|
|
'00/1/27 at noon |
|
Launch Coundown begins |
|
'00/1/28,17:30 EST |
|
| @ |
Power reactant storage and distribution system
loaded |
|
|
'00/1/29 |
| @ |
Rotating Service Structure retracted |
|
|
'00/1/30 at about 18:30 EST |
| @ |
External tank loading |
|
|
'00/1/31, 04:00 - 07:00 EST |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| @ |
TARGET LAUNCH TIME: |
'00/1/31,12:47 EST |
|
|
| @ |
TARGET LANDING TIME: |
'00/2/11,16:55 EST |
|
|